B513 Planning Meeting, 8th August 2002
Present:
Nigel Baddams, Tony Cass, Anne
Funken, Jukka Lindroos, Jose Miranda-Vizuete
1.
Previous Minutes
- Approved with minor corrections. The Divisional Request for the
UPS systems was created.
2.
Substation Planning
- Gutor have supplied information about the cooling requirements
for their systems. Unfortunately these describe the “best case”
requirements but the air conditioning system must be sized for the worst
case scenario. The technical details from Gutor show that, unlike the MGE
solution, filters to cope with 3rd harmonics would be required.
This leads to an increasse in the space required.
- Anne has just received details of the power needs of the hvac systems;
some time is needed to study these.
- Anne showed a very preliminary substation layout assuming 2MVA
transformers and MGE UPS systems. This shows that a 19.4m long bunker is
insufficient—extra space is required for general services switchboards.
- Nigel and Jose consider that a bunker longer than 19.4m is
possible, but any part beyond this length must have a
more restricted headroom if access to the barn door is to be
preserved. At first sight, 2.8m headroom is achievable; this is less than
the 2.95m desired, but the requirements could perhaps be reduced.
- Having analysed the loads further, Anne considers that a
solution with 3 2.5MVA transformers is required in order to cover loads in
B613 and B31. This solution also allows more optimal use of the existing
UPS room if the physics UPS does have to be split for cooling purposes.
- The air conditioning arrangements for the physics UPS is still
the major concern. Jukka calculated that 100 air changes/hour would be
required to cool a 200kW load in a 3.5m high room with an area of 160m2. Assuming the same rate of air change (a rate Jukka considered
to be at the limit of tolerability) two of the required three UPS units
(each 3 modules and a spare) and their associated batteries could be
housed in the existing UPS rooms. Space nearby would have to be found for
the 3rd unit.
- Tony stated that we should assume the 3x2.5MVA solution is
adopted and plan accordingly (see point 3.1). The
following issues will be followed up before the next meeting.
- Nigel and Jose to better define
the maximum headroom for the part of the bunker under the access to the
barn door. Anne to check if the clearance requirements for the LV switchgear
can be reduced below 2.95m.
- Anne to prepare a layout with UPS
modules split 8+4.
- Jukka to study the provision of
air conditioning for the UPS and for the bunker, possibly involving the
use of S-401 for hvac equipment (but see 3.2b below).
- Jukka to establish which ducting
in the S-206 corridor must be preserved and Nigel and Jose to discuss
door locations for the bunker accordingly.
- Tony to investigate possibility of
moving the PABX from S-049.
3.
Changes to support active load
of 4MW
- The more information becomes available about the Itanium
processors, the less the assumption of a constant load of 100W per box
seems realistic. A better assumption seems to be a constant efficiency of
10SpecInt2000/Watt. With this assumption, the power demand in 2008 will be
2.4MW and could rise in later years. IT is therefore interested in the
feasibility of supporting an active equipment load of up to 4MW.
- The responses were as follows
- In terms of electrical
distribution, the density of normabarres would have to double. This is
achievable and could be supported either by doubling the number of PDUs
or by installing larger PDUs initially. In either case, the normabarres
could be installed over time.
- The size of the substation (and
the number of transformers) would have to double. At first sight, this
could be accomodated as the bunker could have a length of up to 42m if
extended to the corner of B513. Access to the extended portion would be
more limited, and possibly at the cost of demolishing S-401.
- Phased construction of the bunker
is possible if the end-wall nearest B31 is built appropriately initially.
However, phased construction would probably lead to a sub-optimal layout
of the substation and thus might not be possible if the space is too
limited.
- The air conditioning capacity of
the machine room could be increased above 1.5kW/m2 by blowing cold air below the false floor rather than from
above. This would require a substantial modification of the air
conditioning system, however.
- Provision of the necessary amount
of chilled water would require additional (or even replacement) chillers
and installation of new pipework with a greater cross section. This
applies whether the chilled water is supplied to air conditioning units,
directly to water cooled equipment (or racks) .
- Tony asked that these issues be studied further, although the
priority for the moment remains the preparation of the 2.5MW solution.
4.
Machine Room Upgrade
- Anne has made an initial study of the possible power
distribution in the machine room. A total of 18 PDUs equivalent to those
in the vault would be required. When UPS arrangements are taken into
account, 14 PDUs could be used completely independently of the vault, but
4 would be usable only if companion PDUs in the vault were not used.
5.
AOB
- Anne commented that we still need to understand how the cold
water pumps are powered and the implications of this for the battery
lifetime for the 200kW UPS.
- Anne asked for some technical information about equipment with
dual power supplies. In particular, do these systems have one input
labelled as the priority input? If so, this should be connected to the PDU
which is supplied by diesels.
- Next Meeting: 14:00 on Tuesday 27th
August.