B513 Planning Meeting, 4th October 2001
Present:
Tony Cass, Anne Funken, Jukka Lindroos, Denis Raffourt, Dave
Underhill
1.
Vault Zoning Issues
- Tony explained that the purpose of the
meeting was to agree the relationship between
a. the
“fire-curtain”/air conditioning zones in the vault, by default 3 in number, and
- the electrical
distribution zones, by default 4 in number.
Since we plan to cut the electrical supply to
equipment if any smoke is detected, the obvious question is whether or not we
should divide the room into 4 zones, albeit at the cost of additional air
conditioning equipment.
- Overall,
the conclusion was “no”. Although there would be some gain (in that,
potentially, fewer systems will be powered off when smoke is detected),
this does not outweigh the extra costs involved (8 air conditioning units
would be required, not 6; although these would have a lower rating, the
costs would be very similar). In particular, Denis Raffourt commented
that, given the sensitivity of the detectors, any smoke in the room would
soon be detected in all zones.
- Careful
consideration needs to be given to the power supply arrangements for the
air conditioning units. If there is smoke in one zone and the air
conditioning units in that zone are stopped, smoke may be pulled to other
zones if the air conditioning units are left running.
- Anne and
Denis questioned whether or not the “critical computing infrastructure”
should be located in the middle zone. It was recognised that this location
minimises the overall length of network cables, but the middle zone is
most open to contamination from smoke in adjacent zones.
2.
Smoke Detection Equipment
- It was
agreed that Denis Raffourt would cost the following.
- A high sensitivity smoke detection system to be installed at
ceiling level in each “fire-curtain” zone. Any alarms from these systems
will lead to the Fire Brigade being called.
- A lower sensitivity system located at the air intake to the
air conditioning units (recirculated air). Coincidence of alarms from
this and the high-sensitivity system in a given zone will lead to power
being cut for all computing equipment in the zone concerned.
- A detection system for installation under the false floor.
There was some doubt as to whether or not such a system would be needed.
On the one hand, it could indicate to the fire brigade that the smoke
source was under the false floor. However, the air-conditioning
arrangements (with air being recirculated and blown up through the false
floor) are such that any fire/smouldering under the false floor will
trigger the other smoke detection systems.
3.
AOB
- Jukka
Lindroos will cost a water detection system; sensors to be placed close to
the air conditioning units.
- Tony asked Anne and Jukka for a list of equipment that
could, potentially, be provided by Portuguese companies as part of an
in-kind contribution to the LHC Computing Grid Project.
4.
Fire Safety Issues
- Shortly
after the meeting, Fabio Corsanego came with the results of various
calculations on the Fire Prevention arrangements proposed. These
calculations indicate that smoke curtains of 50cm together with smoke
extraction capacity of 10m3/s will contain smoke from a fire
with a power of up to 2,700kW within a given fire-curtain zone.
- A fire with
a power of 2,700kW is a relatively large fire. In a “medium development’
scenario (likely, but not certain), it would take 15 minutes for a small
fire (initial flames) to develop into a fire of this size, more than ample
time for the Fire Brigade to arrive. Additionally, cutting equipment power
immediately smoke is detected reduces the risk that smouldering develops
into an initial fire, further extending the acceptable delay before Fire
Brigade intervention.
- Overall,
therefore, Fabio concludes that the fire protection measures for the vault
are acceptable.