B513 Planning Meeting, 18th May 2001
Present:
Tony Cass, Anne Funken, Jukka Lindroos, Dick Minchin, Dave
Underhill, Mario Vergari
1.
Civil Engineering Work for the Vault
·
Tony presented a plan to remodel the Vault. The
relevant elements of this plan were
a.
Removal of S-407, 408, 409 & 432 (former MG room
ventilation rooms), integrating the space into S-034
Here, Jukka commented that these areas house fresh air input and hot air
extraction ducts and that he planned to make use of these for smoke extraction
(see below). It was concluded that these rooms could be removed, but that the
plenum between S-030 and S-034 should probably remain.
b.
Removal of S-406
c.
Construction of a wall along the line of pillars separating
S-412 and S-040. This wall to extend into S-411 (the UPS battery room), cutting
this in half.
Anne commented that she had been considering housing a future UPS system in
B513, thus reducing the size of any external “energy centre”. Constructing this
wall would severely limit the technical space within B513. Given this point, it
was agreed that building a wall in line with the existing doors into S-411
could be considered. This would make some 200m2 available for use as
technical space.
·
Anne presented an initial estimate of 161K for
a. Removal
and evacuation of existing false floor and partitions,
b. Painting
the concrete floor,
c. A
false floor of 1200, and
d. Stairs,
access ramps and barriers.
2.
Smoke Extraction for the Vault
- Following discussions with Fabio Corsanego of TIS, it is
clear that provision for smoke extraction in the vault is required. Jukka
has reviewed the Swiss and French codes for computer centres (the latter
is considered as the reference for CERN), and, for a room the size of the
vault, provision must be made for an air flow of 10m3/s.
·
Jukka considers that these requirements can be met
without the need for overhead ducting.
a.
Smoke can be extracted via the chimney above the archive
store—although this will require the installation of a fan. As noted above,
smoke could be routed to the chimney either via the plenum between S-030 and
S-034 or via a duct on the S-030 side (smoke is extracted at ceiling level
only).
b.
Fresh air can be routed to the “far side” of S-034 via ducts
under the false floor which connect to the fresh air inlets in S-406 and S-407.
- Jukka drew attention to the fact that a fire in winter
could lead to an inrush of air at temperatures as low as -12°C.
If this could damage equipment then a heat exchange system to warm
incoming air would be needed (and could be provided easily given the
heating plant already present in B513).
- Tony mentioned that he and Dave had discussed some
aspects of fire protection during a visit to discuss access control. Marc
Vadon had suggested that barriers be installed at ceiling level to limit
the spread of smoke. This was felt to be especially important as it is
unlikely that computer equipment will ever be halogen free—and so even a
small fire could cause extensive smoke damage.
- It was felt that such a system of barriers would only
make sense if they were installed in parallel rows at right angles to the
S-030/S-034 plenum. However, Jukka was concerned about the potential
interference with air flow in normal circumstances; he will discuss this
issue with Marc Vadon.
3.
HV Supply and UPS for B513
- Anne had prepared a paper with size and costings for
various UPS options. The key points are as follows.
|
|
|
|
|
Space
|
|
|
|
Load
|
Time
|
Cost
|
UPS
|
Batt.
|
Comments
|
|
1
|
2MW
|
10’
|
630K
|
80m2
|
60m2
|
Required to cover brief interruptions and auto-commute
between Swiss & French supplies
|
|
2
|
200kW
|
30’
|
80K
|
10m2
|
18m2
|
Additional protection for the basic computing
infrastructure (but if auto-commute fails, power outages of up to 120’ can be
envisaged).
|
|
3
|
200kW
|
120’
|
130K
|
10m2
|
75m2
|
Given the number of battery modules required, a static UPS
solution may not be advisable for this load/time combination.
|
- In addition to the MTBF concerns for the 3rd
solution (which Anne will be discussing with MGE next week), the
air-conditioning implications also need to be understood. There may be a
requirement to support air-conditioning in the vault if some 100kW of
equipment is to be kept running for 2 hours.
- Equally, the air-conditioning load has to be included if
the full equipment load has to be supported during power cuts of more than
10 minutes. A standalone static UPS system is unfeasible; either diesel
backup or a rotary UPS must be installed.
- Housing a combination of solutions 1+3 in B513 does seem
possible, especially if the extra technical space is made available.
However, arranging an orderly installation and changeover from today’s UPS
could be rather difficult.
- Planning for the inclusion of B513 in the 18kV loop
continues—including costings for an “energy centre” that could house
either a static or rotary UPS system. It was noted that issues such as
noise and air intake/exhaust provision have to be taken into account whrn
housing diesel engines (either alone or as part of a rotary solution).
These factors might prevent installing diesel engines in B513 and would
increase the cost of an external energy centre.
- Finally, Anne was concerned that the upstream electricity
supply would not be able to support the additional 500kW load being
projected for the vault until B513 is included in the 18kV loop. Tony
pointed out that, at least initially, it was more a question of installing
equipment in the vault rather than in the machine room and power
consumption would not leap by 500kW. On this basis, Anne agreed that there
would be no problem installing equipment in the vault, but said that power
consumption could not increase by more than 200kW.
4.
Low Voltage Distribution in the Vault
·
Anne presented an initial proposal for a low-voltage
distribution system in B513. In addition to meeting the likely power demands,
this solution makes use of outlet boxes pre-connected to busbar trunking
(Normabarres) in order to limit the need for specialised electrical expertise
when connecting equipment. Those present from IT commented that
a.
it was not acceptable for sockets to be provided at floor
level; all cabling must run under the false floor, and
b.
both single- and 3-phase sockets must be provided.
Tony also commented that Anne’s costings for the
distribution system should end at the sockets. The costs of any cabling and
equipment required at the rack level are covered elsewhere.
- The proposed distribution scheme includes normabarres for
physics load and for basic computing infrastructure. Equipment with dual
power inputs could be connected to both networks. There is no provision
for a “second level”switchboard-style system connected to two normabarres
in order to provide a dual-feed supply for equipment with only one power
input. However, this could be added.
·
The proposed switchboards support a 400A load, trip the
output feeders (normabarres) on power loss and support remote switching (on or
off) of the outputs. One 400A switchboard would power four 100A normabarres,
each of which can support up to seven racks of 40 PCs. Switchboards that would
support six 100A could be available from July.
- Anne’s costings were worked on the basis of support for a
CPU farm for a single LHC experiment. It was agreed that a proposal for
equipping the vault with power outlets at a reasonable granularity should
be prepared. A very preliminary review suggested that three switchboards
would be required to support the physics load with further switchboards
for the basic computing infrastructure and for the air conditioning units.
5.
AOB
- It was noted that the B513 goods lift is scheduled for
renovation in September/October.