Minutes of the B513 Planning
Meeting, 15th Sep
Present:
Roland Bachelard, Tony Cass, Anne Funken, Jukka Lindroos, Dick Minchin, Dave
Underhill
1.
Previous minutes
- When discussing the action list, Jukka pointed out that there
is no active desenfumage for the machine room; all that is done is to stop
the recycling of air (and smoke). The future needs should be discussed
with the fire prevention unit.
2.
B513 Items for 2001 IT Budget
2.1.
Access Control
- The replacement access control contract
is scheduled to be discussed at a Finance Committee before the end of the
year. However, the earliest anything could be installed around B513/B31 is
mid-2001.
- The quote in November ’99 was 600KFF for controlling external
access to the buildings plus a
further 225KFF for controlling access to the machine room. This quote does
not include cables and work to be provided by ST. Roland believes this
will add 20KCHF to the total but will check. It is assumed that the
central control unit for the new system would be placed in the operators area.
2.2.
UPS Batteries
- The cost for replacement UPS batteries
depends on the guaranteed lifetime and is roughly 75K/module for a 10year
guarantee, 72K/module for a 4 year
guarantee and 42K/module for a 2 year guarantee. However, the expected
lifetime for the latter batteries is 5-6 years given the storage
conditions at CERN. As it is anyway imagined that a further replacement
will be required before LHC startup, it was agreed that we should propose
to purchase batteries at 42K/module. Roland will ask for an update quote
and check that the batteries could be installed in 2000 if the money
becomes available.
- It was noted that these batteries would only maintain the
nominal 5minutes continued supply at the rated load (400kVA/module).
Although the autotransfer between the Swiss and French supplies takes over
within 8 seconds, there would be a much greater period without power if
the supply is cut following an incident within CERN. However, the aim for
the moment is just to ensure continued running of the current system. The
overall UPS picture will be studied as part of the B513 redevelopment.
2.3.
Vault False Floor
- To start providing additional equipment
area, Tony suggested installing false flooring at the west end of the
vault (to the right entering through the doors by the main B513 lift).
Roland will ask for a quote, but the price is expected to be around
250CHF/m2. The cloisons surrounding S-037, S-039, S-041 and
S-040 would have to be removed and we also need to understand whether or
not te doors into S-413 and S-411 need to be maintained (either for access
or emergency exit purposes).
- With current packing densities, this area (roughly 300m2),
could support 60-70 racks of PC servers (40 PCs/rack). The power
consumption of these racks has been measured at 3.3kVA. The electrical
supply for the area should therefore be for 250kVA. A quote provided
earlier in the year was 53KCHF for a switchboard and associated
normabarres to support up to 150kVA.
- Similarly, the air conditioning should be able to cope with
this level of heat production. However, installation of the air
conditioning capacity can be phased as PC systems will be installed
gradually. One possible solution, therefore, is to install ducts now that
connect to the existing air conditioning units (which have 80kW free
capacity). These ducts would then be connected to more powerful units to
be installed later. Jukka will investigate the pricing.
- It was noted that the air conditioning for the vault is limited
to 500W/m2 if conditions have to be acceptable for people to
work in the room.
- Anne commented that we should study the rate at which the
temperature would increase without air conditioning to understand if the
equipment has to be connected to the UPS. (Earlier studies have shown that
with 2MW of equipment in the machine room, the temperature will rise by
5ºC within 40s. This has important implications for the sizing of the UPS
and also for the diesel backup arrangements.)
2.4.
Fire detection
- Denis Raffourt should be contacted to
see if there would be any cost to IT for renovating the fire detection
equipment in B513
3.
Longer term B513 planning
- It was agreed that we should now start
to look more closely at the possible future options for the electrical
supply to B513. This should wait until Anne has understood the various
factors affecting the lifetime of the current equipment (such as age,
rated lifetime and future availability of spare parts).
4.
AOB
- Roland will check the proposed dates for
maintenance of the UPS ane Emergency Power off system in 2001. As in 2000,
continuity of electrical supply would be guaranteed during the tests but
there would be no UPS cover for roughly one hour.
- Removal of the obsolete pipework in the
vault is scheduled to start in the week of September 18th.
- It was agreed that the next meeting
would be held at 2pm on Thursday 5th October.
5.
Actions
5.1.
Completed
Who
|
Action
|
Assigned
|
Completed
|
Jukka
|
It is possible to have 9 air conditioning
units run simultaneously.
|
30/05/00
|
15/09/00
|
Anne
|
Arrange quote for removal of the existing
MG room cooling equipment.
|
09/05/00
|
15/09/00
|
5.2.
To be done
Who
|
Action
|
Assigned
|
Anne
|
Understand practical lifetime of
electrical supply equipment
|
30/05/00
|
Tony
|
Ensure UPS battery replacement is included
in IT budget for 2001
|
30/05/00
|
Tony
|
Arrange discussions with TIS about the
requirements for general or localised emergency power off systems.
|
30/05/00
|
Roland
|
Check supplemental costs associated with
access control replacement.
|
15/09/00
|
Roland
|
Obtain updated quote for UPS batteries
with 2 year guaranteed lifetime and check to see if these could be supplied
during 2000
|
15/09/00
|
Roland
|
Obtain quote for false floor installation
in west end of the vault
|
15/09/00
|
Roland
|
Obtain quote for providing electrical
supply for load up to 250kVA for the west end of the vault
|
15/09/00
|
Jukka
|
Investigate and cost options for providing
air conditioning to cover equipment installed at the west end of the vault.
|
15/09/00
|
Tony
|
Contact Denis Raffourt to discuss possible
changes to the fire detection system in B513
|
15/09/00
|