17th September |
|
The partitioned areas used for PDP storage. These will be removed. |
|
The view from the big blue doors with the corridor to the MG room on the
left. This will be blocked up and all of this corridor will be in the
controlled area. |
|
|
The new technical room for the air conditioning will block access to this
emergency exit... |
|
... which is maybe just as well since this is where it leads! |
|
|
This room (S-406) houses the original air conditioning equipment for the
vault. This will all be removed. The unit at the back of the room serving
the UPS batteries and telephone exchange will stay, but in the new
technical room. The duct from this unit will be raised to provide more
clearance. |
|
|
This air-conditioning unit, and associated ducting, was added when the IBM
robots were first installed in the vault. It will be removed and stored
for use elsewhere at CERN. |
|
|
These rooms (S-432 and others) housed the air conditioning system for the
MG room (S-030). The ceiling is lower than the vault (as can be seen in
the two pictures on the right) and is made from concrete poured on top of
corrugated steel. This is the "dalle holorib" to be demolished. |
|
|
4th December
The PDP storage areas have been dismantled, as has the partitioning hiding
the gap above the dalle holorib. Dismantling of the false floor has
started. |
|
|
10th December
The false floor is down and the Saleve side door has been removed.
Unwanted cables in the MG room are being removed. |
|
|
14th December
Most of the old electrical cabling has been removed |
|
|
10th - 17th January
Dismantling the air conditioning ducts. |
|
|
9th February
The cables from the UPS to the power distribution units in the machine
room run through a wall that is to be demolished. These have to be
rerouted for safety reasons and so the computer centre shuts down! |
|
|
12th February
Lifting up the air conditioning duct for the UPS battery room. |
|
|
All the walls marked for demolition (inside the MG room, the MG room and
vault air conditioning rooms) |
|
|
A picture of the rubbish and some general views. |
|
|
12th - 18th February
Removing the original hvac equipment. The bits that are left will be
removed once the wall has been demolished. |
|
|
18th February
An empty vault! |
|
|