B513 Planning Meeting, 12th November
2004
Present: Nigel Baddams, Tony Cass, Serge Deleval, Anne Funken, Jose Miranda-Vizuete, Tim Whibley
1. Overall, the advancement of the electrical installation work is reasonably satisfactory. Installation of the 18kV cables will start once the caniveau extension has been joined to the galerie technique; work on this will start early next week and last 2-3 days. The 48V equipment is scheduled to arrive by the end of November. The tender for the critical UPS will be opened on November 19th; delivery is foreseen for February 2005.
Date |
Step |
Mid-Jan |
Transformers connected into 18kV loop but running without load. |
Mid-Jan-end-Feb |
Cables installed between existing PDUs and new substation. Work takes 6-weeks overall, but PDUs can be switched over as soon as the new cables reach them. |
Early Feb |
General services (i.e. offices, lighting, …) moved. There are 9 PDUs in total; can switch 4 per day. Foresee two weekends for this. |
Feb/Mar |
Critical services UPS installed and commissioned. |
Late-Feb/early-Mar |
HVAC PDUs moved over. There will be temperature rises for short periods, especially in the vault. |
Late March |
“Critical” PDUs moved over. This can be done without interruption for the in-service PDU in the machine room, but an interruption is required for the vault PDU. Equipment with dual power supplies should not be affected, however. |
Mid-March |
Physics PDUs moved over.
|
Late-Feb OR late-Mar |
Physics UPS moved between substations. This could take up to two weeks to complete. However, the UPS cannot be in two places at once! PDUs moved (a) before or (b) after the UPS will also be without cover until (a) the UPS or (b) the PDUs themselves are moved. |
1. Installation of the ducting on the left hand side of the machine room has been arranged as an avenant to a contract for work in the ATLAS pit. The initial quote for this work, 175KCHF, is significantly cheaper than the 350KCHF estimated earlier in the year. Work is expected to start on November 15th and last until the end of January.
2.
It was
proposed to install ducts some 30cm in front of the Jura side wall in order to
avoid the wooden separation between the machine room and the corridor. However,
a visit to the machine room showed that doing so would reduce the free space
behind first row of equipment racks to an unnaceptable extent. Serge will thus
ask for the ducts to be installed against the wall; this will entail some
modifications to the recently installed plaster-block wall.
3. Work to install the LHS floor grilles should probably be dealyed until at least January, in order to allow completion of other work—including installation of trays for the cables supplying the new PDUs. However, Steel Systems could be called earlier to review any false floor structure modifications needed to accommodate the new ducts. Serge would also be interested to see if there are options for grills or tiles with a reduced open cross-section for use near the edges of the room where ht eair pressure is highest.
1. The electrical equipment in te existing substation can be dismantled from early April. This is expected to take about 4 weeks, for a cost of around 30KCHF. The remodelling work, which is expected to take around two months, could thus start in May. There are three aspects to the work:
a. Extension of the second caniveau. The intention is to have this work done by Belloni under the contract for bunker construction.
b. Demolition/remodelling of walls & doors. This is estimatd to cost 80-100KCHF so a price enquiry is needed; there is plenty of time for this process before the work needs to begin.
c. Construction of a false floor: to be managed by ST/EL; expected cost of around 50KCHF.
2. To enable the new UPS system to be installed in early 2006 (or, preferably, late 2005), the tender needs to be adjudicated at the Finance Committee of September 2005. The process thus has to start early in 2005 with a Market Survey sent out by the end of January.
1. A new coordination plan is needed. This should show
a. the actual positioning of equipment on the RHS,
b. the new rack and normabarre layout for the LHS