B513 Planning Meeting, 3rd
February 2004
Present:
Tony
Cass, Anne Funken, Jukka Lindroos,
Jose Miranda Vizuete, Tim Whibley
1.
Previous Minutes
- 2.4) Delivery of the 18kV cells is confirmed for the second
half of March; the middle room of substation should be ready for then.
2.
Substation Status
- Various small items:
- Preparation of
the final finishing work continues despite the poor weather.
- Additional
openings are being made for the HVAC ducts.
- Schulthess have some
problems with the installation of the false floor due to variations in
the level of the concrete. These are within the acceptable tolerance,
however, and so Schulthess will have to make the necessary adjustments.
- Installation of cable trays and lighting
will start in the second half of March.
- ST/EL are still investigating
possibilities for transparent transformer housings; there is some
difficulty in ensuring adequate ventilation as it is apparently not
possible to create the louvered grills in plexiglass.
3.
Machine Room Upgrade Status
- A plan for the location of the grills in the false floor is
still needed—and must be provided by the week of February 23rd
to allow time to move cut and damaged floor tiles. Jukka will contact Nigel
Baddams about this.
- Steel Systems have quoted €2,700 for the modifications to the
false floor to accommodate the ducts along the Salève wall. However,
various modifications were shown on the plan sent to Steel Systems and it
is not fully clear which are covered by this quote. Jose and Jukka will check.
- Although ducts will be placed under barn wall now, connection
of the ducts to the cold air plenum will be planned in parallel with plans
for remodelling the barn. It would be possible to have one descending duct
near the Salève side with a horizontal duct under the false floor rather
than multiple ducts down the barn wall. Anne commented that the old
canalis distribution along this wall will need to be removed.
7.
Losinger have quoted CHF22K for
the creation of the three holes in the floor of the cold air plenum to connect
the vertical ducts in the columns along the Salève wall. Jose will place the
order although we still need confirmation from J. Treleani (the architect for
the bunker) that no special reinforcement is needed for the building. Various
issues related to this work were discussed:
a.
the risk of transmission of
dust through the machine room: this should be minimal, but will be checked as
work progresses and protection added if necessary.
b.
the need to rework the drains
from the HVAC area that run through the floor to connect to the downpipes for
rainwater: Jukka needs to trace the required
cuts in the plenum so that the impact can be understood.
- can the holes nearer the archive store be
cut now given that equipment in that area, including electrical tableaux,
is in service? This, and other safety related issues will be discussed
during the work inspection planned for 10am on February 24th.
- Responses to the price enquiry for the installation of ducts on
the right hand side are due for the next week; the order should be sent
out by February 13th.
4.
B513 HVAC Planning
- ST/CV now have a draughtsman working on
the project, but Jukka considered that it would take up to three months to
prepare a full model of building, including the routing of chilled water
pipes and their state.
- It was not possible to check the state of
chilled water pipes during the week of January 26th. Jukka will
contact Serge Deleval to find out when this will be done. Equally, the
test with all stations running (in order to measure noise levels) still
has to be scheduled.
- There was some discussion of the need for
a thermal cut out system. If this were to operate at the PDU level,
modifications would be needed to the PDUs that have been installed in the
machine room. However, as the risk of failure is low, it would be
acceptable for this to act at the UPS level and cut all physics services.
This, though, would require modifications to the 400V switchboards now
under construction. It was agreed that we first need to understand the
rate of temperature rise in worst case scenario. This will be prepared by
Jukka.
5.
AOB
- Marc Collignon has prepared a new plan
for the network area, including the move of racks to provide adequate
maintenance clearance for the PDUs. The installation of normabarres in
this area may be arranged accordingly; this area will be used permanently
by CS so there is no need for a generic arrangement.
- Next Meeting: 14:00, Friday 27th
February