B513 Planning Meeting, 21st
November 2003
Present:
Tony Cass, Anne Funken, Jukka
Lindroos, Jose Miranda-Vizuete
1.
Previous Minutes
- 3.4) ONET are preparing an estimate for the cleaning of the
false floor. Tim has stressed that this work should be carried out before
Christmas.
2.
Substation Status
- The order for the 400V switchboards will
be created during the first week of December. The order for the transformers
is expected early next week; this has been delayed as an avenant to the contract
was required.
- Belloni cannot create the caniveaux
under the transformers with the transformers in place as planned. Given
that complete removal of the transformers is a lengthy process, creation
of at least one, and possibly both, of these caniveaux will have
to be done after the new substation is commissioned. This has two
consequences.
- Anne needs to replan
the commissioning of the substation, and particularly the cable routing,
to avoid requiring these caniveaux—and then arrange for the rerouting of
cables once they have been created.
- We need to
discuss with Belloni whether or not any part of the caniveaux can be
constructed already or if all should be left until later. Both options
have problems, but it would seem best to construct at least part of the
caniveaux now to ensure that there is no requirement for access to the
substation once it is in operation. Jose will discuss this with Belloni
and also with SPL as the contract and payment implications need to be
understood.
- The waste water pipe in the barn wall has
been traced to the sink in the barn. This will be disconnected.
3.
Machine Room Upgrade Status
- Following discussions during a visit
from Steel Systems, the free surface area required has been reduced by
accepting an increase in the air velocity (from 1m/s to 2m/s). The layout plan should be updated to
reflect the reduced number of grills and also to indicate the position of
the new ducts for the underfloor air flow.
- Three PDUs have arrived and installation
has started. Delivery of the remaining PDUs is expected during week
48. Placement of the PDUs in the
room allows for installation of filters should this be necessary
later. Anne considered that it
should be possible to power the normabarres as from the beginning of
January.
- Although the power available on the
right hand side will be restricted initially by the limited number of
connections at the UPS level Anne does not expect there to be any problem
in supporting all of the equipment to be transferred from the left hand
side. We will, however, have to take care in equipment placement as each
PDU can be run at most at 50% of the nominal capacity.
- Jose reported that the plaster block
wall under the false floor had been completed as foreseen, the expansion
joints in the false floor had been covered and the holes in the Saleve side
wall filled. Although the plaster
block barrier could be continued behind the networking area there is
probably little interest in doing this work at present. The plaster blocks
should be stored inside until the installation work restarts.
- Jukka will arrange for removal of the radiators
along the archive store wall and also the sink nearby.
4.
B513 HVAC Planning
- There has been no change in the overall
status of the HVAC planning. However, the pipework will be cleaned soon
and this will allow x-raying of the pipes to check their state.
5.
AOB
- Next Meeting: 2pm, Monday 15th
December.