B513 Planning Meeting, 28th May 2003
Present:
Tony Cass, Anne Funken, Jukka
Lindroos, Jose Miranda Vizuete, Tim Whibley
1.
Previous Minutes
- 2.1c) There will be no filters in the
air intake.Jukka commented that it would be possible to place a smoke
detector in this air inlet which would shut the fire dampers just as in
the case of a fire in the LV room.
2.
Substation Planning
- The substation tender was issued on
schedule and some companies have contacted Jose for further details.
- Now that the hvac arrrangements are defined, Anne will contact
Denis Raffourt concerning the smoke detection details. It was noted that
there is no urgency in this area as it is a fairly standard installation.
However, an estimate should be prepared.
3.
Barette Protection
- Anne commented that all equipment must
be equipped with an internal fuse to protect against damage. Fuses at
either the normabarre connection or barette level are to prevent damage to
cables, not to equipment.
- Ideally, there should be no requirement
for a fuse/breaker at the barrette level provided that the sum of loads on
the individual sockets is less than the rated power for the internal
cabling and the cable connecting the barrette to the normabarre. However,
this cannot always be assumed and so it is safest to have a fuse/breaker at
this level even if there is no strict requirement. An additional advantage
is that if there is any problem, it is easier to reset or replace the fuse
at the barrette level than to have to replace the fuse in the normabarre
connector under the false floor.
- In terms of the breaker vs. fuse choice,
we should anyway make sure that the inrush currrent for the equipment
connected to the barette stays within the rated load. On this basis, a
breaker has the advantage in terms of ease of reset. It was noted, however,
that the remotely addressable power bars that we are considering are
equipped with fuses.
- If we are to limit the number of systems
connected to a normabarre to maintain the inrush current below the
barrette rating, a maximum of five of the current disk servers can be
connected per 16 A normabarre. In principle, it ought to be possible
to connect 13 CPU servers per barrette, but these have a maximum of 10
sockets.
- Tim noted that, given the many barrettes
required to support the multiple independent power supplies, the placement
of the disk servers is determined by the availability of normabarre
connections.
- In response to a query raised during the
discussion of remotely addressable power bars, Anne stated that the normabarre
connection supports a current of up to 63 A.
4.
Machine Room Planning
- Anne, Nigel and Tony have discussed a
room layout that places equipment racks back-to-back in 18 m long
rows in three blocks in the machine room. Each row contains six “Mario
racks” or up to 18 19” racks. Although the rows are 18m long, they will be
supplied by two 9 m normabarres placed end-to-end. This is based on
the measured power consumption of
- “old PCs”:
100 W per PC with a power factor of 0.7 where each 100 A
normabarre is limited to a useful capacity of 50A/phase and can support
3.5 “Mario racks”, and
- “new PCs”: 200 W per PC with power factor
correction allowing the use of the full 100 A/phase normabarre
capacity.
- Based on recent experience, and given
recent changes to European standards for PC power supplies, we consider
that it is reasonably safe to assume that power factor correction will be
available on all future systems purchased. On this basis, we do not need
to allocate space for filters in the PDUs and each PDU could therefore
support up to 6 normabarres. Given the room layout proposed and to allow
some scope for future expansion, we will install one PDU per double row of
racks, each PDU supplying four 9 m normabarre lengths and one
18 m normabarre length. Twelve PDUs are required to support the
physics equipment and the operators area.
- It is proposed to locate critical
equipment in a strip about 5 m deep along the back wall of the
machine room. One or two PDUs in tis area would be required to supply both
the normal power and the diesel backed power through multiple 3 m
normabarre lengths. The PDUs in this area would also be used to supply the
modem/fibre rooms in the Salčve side corridor.
- Anne will discuss the proposed layout
within ST/EL to establish the possibilities for reusing the existing
normabarres and will then contact the contractor to establish an estimate.
It was considered that the installation work could start from September.
- Jukka commented that we must be careful
if racks are placed back to back. Experience in the vault has shown that
convection cannot generte the air flow necessary to keep the temperature
at a reasonable level; perforated tiles are needed to generate a forced
upward air flow. This reinforces the view that we should be converting the
hvac arrangements in the machine room to create an air flow from the false
floor. Unfortunately, planning is still at an early stage and will take
some time to complete given the lack of drawing staff in ST/CV.
Fortunately, the ducts would natrually be placed along the north and south
walls of the room whilst most of the PDUs would be along the east and west
walls.
- Given the shortage of planning staff in
ST/CV and other projects, Jukka considered that work on the chilled water
piping in B513 would not be possible until the winter of 2004/5. Other work,
such as the installation of the necessary duct work and modification to
the cooling stations, could in principle be done at any time as the
current equipment is never fully loaded. However, Jukka felt that even if
this was possible in principle, the ST/CV staff situation would push the
work to 2005.
- Tim will contact Steel Systems to see if
they can still provide perforated tiles in the required 61cm x 61cm
format. If these tiles aren’t easily available we could consider grids
between the back of racks, but not in the corridors. Jose considered that
the perforated tiles would cost 150-180 CHF/m2. The current layout has 200 m2 of perforated tiles for a total cost of 30-36 kCHF
- Jose has investigated the level of separation
between the machine room and the rest of B513. This has shown that the open
part along the back corridor extends only across the width of the modem
& fibre room; the division extends under the corridor on either side
of this area. Although the machine room is completely isolated around the
false floor plenum, the separation is only by wooden barriers and there is
no insulation where cables pass through. Thisis probably not adequate in
terms of fire protection. Jose will contact Fabio Corsanego and use the
opportunity to clarify the status of the separating wall between the
machine room and the barn.
5.
AOB
- The formal reception for the hvac units
in the vault took place on Wednesday. There are some points to address,
but the units are now considered as being fully in service and to be
handled by the general ST/CV operations team.
- Tony will be giving a further
presentation of the B513 upgrade status to IT division at 9:30 on June 27th. The presentation will cover the
substation status, including failure modes for the electrical supply, and
the initial planning for the machine room upgrade.
- Next Meeting: 2pm, June
10th in B31-1-012.