B513 Planning Meeting, 6th May 2003
Present:
Tony Cass, Fabio Corsanego,
Anne Funken, Jukka Lindroos, Jose Miranda-Vizuete, Tim Whibley
1.
Previous Minutes
- Approved with minor corrections.
2.
Substation Planning
- Fabio Corsanego reviewed various safety
related aspects of the new substation.
- There is no
particular risk for most of the equipment to be installed in the
substation. The exception is the batteries for the UPS systems and the
possible risk of hydrogen emissions. Howerver, the batteries to be used
will be sealed units of the type widely used elsewhere at CERN.
- The placement of
the dry transformers is acceptable in terms of the level of risk to the
building. Fabio reconfirmed, though, that the barn area by the
transformers should not be used for offices.
- Although the
transformers are placed near to hvac inlets this is acceptable since no
smoke from incidents in the substation will be taken up and circulated
into the rest of the building. The biggest risk is for the existing UPS
room; the air filters for the relevant air inlets (above the LV room) must
be fire resistant.
- The transformers are
equipped with a thermal cut-out. This is transmitted to the TCR as a
level 2 alarm.
- The smoke
extraction provisions (1m3/s per 100m2) were considered adequate.
- Fabio insisted
that the substation rooms be well separated
from the rest of the building to prevent smoke propagation. In
particular, all doors must be smoke resistant for at least 30 minutes.
He considered that this requirement excluded the use of metal doors.
- There was a suggestion
to extend the steam exit pipe upwards by about 3m to ensure that the exit
is well away from any transformers, but this steam exit was not
considered as a risk for the substation.
- Overall, Fabio considered the substation
design to be acceptable, but emphasised the need for smoke detection and
for the fire brigade to be able to shutdown the substation.
- The specification meeting was confirmed for
9:30am on May 9th..
- Anne will be able to attend the Site Committee
and will prepare a presentation, possibly including Nigel’s “photographs”.
The greatest impact will be the reduction of parking space during
construction. Although temporary spaces could be created along route
Gregory, there are usually some spare places in the car park on the Salève
side of B513 so this may not be necessary.
3.
Machine Room Upgrade
- Given recent events, there had been
little time to study the machine room upgrade in detail. Three points were
discussed, however.
- We need to be
sure that the machine room is properly isolated from the rest of the
building. Jose will investigate the current situation before the next
meeting. The biggest impact is likely to be on the cable connections
between the machine room and the modem/fibre room— the future hvac
arrangements for which we must also be uinvestigated.
- Anne has had some
initial discussions with Nigel concerning equipment and normabarre
layout. Tony should contact Nigel to follow this up during Anne’s
absence.
- Anne will
prepare, probably via Marcel Lasne, a list of the existing equipment that
can be used. This will mostly consist of normabarres and some circuit
breakers although there is some chance that parts of the existing PDU
cabinets could be reused.
4.
Lessons from incident on 22nd
April
- It is clear now that we should not use
differential protection on the barrettes. Unfortunately, further study is
needed before we can agree the best replacement solution.
- A failure/maintenance mode analysis is
needed for the hvac systems (and their associated electrical supply) as
well as for the electrical supply for computing equipment. The analysis
should present the costs associated with any additional installations
(hvac units or redundant electrical supply) required to reduce
vulnerability. The sooner such a study is available, the easier it will be
to integrate any agreed changes into the overall planning—both in terms of
work to be done and the financial planning.
- Anne would also like to understand if any
special arrangements need to be made during the installation of equipment
in the current UPS room. In particular, should the cables be routed to the
UPS units from above to allow optimum air supply under the false floor?
Jukka did not consider this to be necessary, but agreed that the placement
of the UPS units in the room should be studied carefully as should the
hvac arrangements for the remodelled transformer area.
- It was agreed that temperature sensors should
be installed in the technical area. These should probably be connected to
the plc that sends information from the vault PDUs to the operators.
- All future ST works in B513 will be
reviewed by the ST Operations Committee to ensure that all side effects
are considered.
5.
AOB
- IT division have identified a supplier
for controllable barrettes. A meeting with the supplier will be arranged
for the week of May 26th such that Anne can be involved.
- Next meeting: 14:00,
Wednesday 28th May.