B513 Planning Meeting, 18th February
2003
Present:
Yannick Body, Tony Cass, Anne
Funken, Jukka Lindroos, Jose Miranda-Vizuete
1.
Previous Minutes
- 2.2: The equipment load to be supported by the HVAC systems in
the event of power failure was clarified as 2.5 MW for first 10
minutes with upto 500 kW in the vault. At the end of UPS battery life
(10 minutes) the load drops to 250 kW with up to 125kW in the vault.
- 2.3c: Cables can be routed to the technical gallery through the
existing openings.
2.
Substation Planning
- It is now clear that two 3 MVA
transformers are required to cover HVAC and general service needs rather
than two 2 MVA transformers. This change has no impact on the space
needed in the safe room, however.
- Cooling 2.5 MW in the machine room requires
decoupling the corridors from the machine room cooling. Individual
corridor units (as in B31) could be considered.
- Jukka confirmed that there will be no
need for access within substation rooms to maintain any hvac equipment.
Access will thus be restricted to qualified electricians so there will be
no need for any emergency power off system.
- Anne presented the general substation schematic.
This made clear the exposure of the HVAC equipment to the failure of a
single transformer. There was some discussion as to how this risk could be
minimised but there is no evident solution as the full HVAC load must be
supplied by the diesels in case of main supply failure. It was agreed that
we need failure rate statistics for the transformers to understand the
extent of the risk.
- During maintenance of switchboards, part
of hvac load will be cut. Maintenance is once every 6 years, failure
extremely unlikely. Need to understand impact of los of equipment.
- On physics side, good protection up to
UPS. Dowstream of UPS, risk to lose up to 1/3rd of equipment at
most. Problem is with failure on hvac side. Risk not to
have enough cooling capacity to keep systems running.
- However, is need
to maintain 18kV switchboard every 6-10 years. This leads to cut in
physics load. Only avoid this today as load can be supported by 1 transfo.
In future, will not be able to escape. Refusing maintenance will increase
risk of failure.
- There has been a suggestion to route
cables in the substation at ceiling level to improve the cable routing on
top of the bunker. Routing at ceiling level may be possible, but cannot be
accepted if there is any requirement for extra free height in the bunker (and
thus to increased construction costs). It was noted that ceiling level
routing also requires a detailed layout of electrical equipment layout
before construction, and is thus disfavoured.
- Anne was anyway concerned that it would
not be possible to achieve an acceptable layout of transformers and cables
on the top of the bunker if all six transformers were located on the
Salève side of the barn doors. It may be necessary to place two
transformers on the B31 side.
3.
AOB
- Next meeting: 9am, Monday 10th
March.