B513 Planning Meeting, 17th January 2003
Present:
Nigel Baddams, Yannick Body, Tony
Cass, Anne Funken, Jukka Lindroos, Jose Miranda-Vizuete, Dave Underhill
1.
Previous Minutes
- Approved with minor corrections
2.
Substation Planning
- Tony reported on discussion that had taken
place with Intel contacts to the CERN openlab. Apparently Intel set a power
budget for processor chips—130W for server CPUs, 80W for desktop CPUs and
40W for portable CPUs. Chip designers must ensure that any features added
will fit within this budget. On this basis, some of the more dramatic
estimates for future power needs seem unrealistic. However, we must not be
complacent either—a maximum possible load of 2.5MW gives little room for
manoeuvre.
- The HVAC arrangements will need some modification in order to
support the full equipment load for 10 minutes. Equally, the redundancy
arrangements for the roof-mounted cooling stations also need to be
understood. Redundancy is not needed for maintenance work (this can be
carried out in Winter), but to understand the
likely impact of failure on the machine room temperature and rate of
increase.
- Jose met the design study bureau on Wednesday (15th
January) to discuss the bunker design. Various suggestions have been made
concerning ways to improve the design and to reduce costs.
- A sloping dalle would be better integrated
with the access to the barn doors and also increase the free height above
the false floor to 2.85 m at the side furthest from B513.
- Unfortunately, a drain pipe running through
B513 parallel to the gallery technique would be cut by the planned caniveau
into the UPS room. The best option is to shorten this caniveau, but this
requires moving the entry to the UPS room which in turn requires reducing
size of S-401 room by 2.5 m. Tony agreed to this proposal.
- The design bureau considers that the
proposed tubes from the transformer rooms to the the technical gallery are
problematic. However, there are, apparently, some openings into this
gallery from behind the transformers which are blocked at present which could
perhaps be used instead. The impact on the arrangement of cables needs to
be understood.
- Use of load bearing internal walls would
reduce the cost by some 30KCHF. In addition, without load bearing walls,
the opening for the cables from the transformers is limited to
2.55 m, less than the 2.6 m required. The argument against load
bearing walls previously was the potential need to remodel the bunker for
a 4MW solution. Now, however, the 18kV room is anyway the correct size
for a 4MW solution and we understand that the changes to the saferoom
depend on the diesel backup situation—and that if any change is needed
here it will a radical change, not a small
increase in size. It was therefore accepted that we would relax the
requirement for future internal remodelling and accept the use of load
bearing internal walls.
- Even with all the cost reductions, however, the initial design
bureau cost estimate is significantly higher than expected. Jose considers
that this is because the unit prices used in the estimation are too high.
If the unit costs of SPIE-Antirust are used instead, the price is closer
to our estimate, but still some 200 KCHF more. Jose felt that the
price would be reduced by open tendering—this is a significant project and
construction companies need work.
- Tony emphasised that the reasons for the cost increase must be
understood—and would, most likely, need to be clearly documented for the
LCG project and directors. Although there is a cost increase due to the
geological conditions near B513, most of the bunker cost increase is directly
linked to the increase in substation space requirements. It was felt that little
of this increase is due to any provision for a possible expansion to 4MW
possibility. Most of the space increase is due to an increase in the
number of 18kV cells and an increase in the size of the safe room now the
HVAC requirements are better understood.
3.
AOB
- Work on the new emergency exit for the
UPS battery room is scheduled to start on February 10th,
although Losinger may start on the 3rd if this is more
convenient for them.
- Jukka commented that some temporary
modifications may be needed in order to ensure adequate smoke extraction
provision for the hvac areas during construction work.
- Next meeting: 14:00
Wednesday 29th January.