B513 Planning Meeting, 5th December 2002
Present:
Nigel Baddams, Tony Cass, Anne Funken, Jukka
Lindroos, Jose Miranda
1.
Previous Minutes
- No comments.
2.
Substation Planning
- There is still concern in IT about the future power demands.
However, it is agreed that we build now a substation to cover a load of
2.5MW in B513. Options to expand to 4MW will be explored in parallel.
- The caniveau position was reviewed. Are two really needed,
especially if they are just 4.5m apart or is one larger caniveau better? Generally,
one large caniveau is preferable, but Anne is concerned about the impact
if this passes into the UPS room. Tony shared Anne’s concerns, but had a
preference for completing all the major civil engineering work in one
phase. After some discussion, it was considered possible to build one
caniveau running under S-413 and routing cables into S-412 via the
technical gallery under the building. This would involve the least
construction overall, but would require the construction of a pit in S-412
once the existing UPS is decommissioned. Nigel, Anne and Jose will check
the feasibility of this solution.
- The revised positions for the air conditioning ducts were
reviewed. There does not appear to be any conflict between the duct
position and sizes and the proposed location of electrical equipment.
There was some discussion about the optimum arrangements for air
conditioning in the low voltage room—mostly on whether or not the cold air
should be distributed under the false floor. This can be decided later,
however, as there is no impact on the size of the duct to be passed into
the room from the S-206 corridor.
- Jose considered that the overall dossier is in a state to be
passed to the design study bureau once the necessary ordering paperwork is
completed.
- Two points were noted.
- There is still no precise information concerning the size of the
equipment to be installed in the LV room. The current layout of the new substation is
based on the maximum electrical equipment needed to fulfil IT’s
requirements and the actual input data, meaning the maximum space needed.
A detailed study is under way and when the precise sizes of the
non-standard LV switchboards are available the layout of the electrical
equipment could be optimized. Detailed recommendations from ST/CV about
their existing LV switchboards may change the arrangements for the supply
of their equipment, altering the layout of the safe room..
- The civil engineering study is launched now—before the
completion of the detailed electrical study and based on the maximum
space needed—due to the delays of the civil engineering phases and the
desire to commission at least the first phase of the substation (high
voltage and safe room). during the 2003/2004 shutdown . Launching the
civil engineering study now means that the bunker will be ready for the
installation of electrical equipment on 3rd November, 2003. As 3rd November is the latest possible date for electrical
installation work to start if it is to be completed during the shutdown,
any delays in the civil engineering work will delay the commissioning of
even the first phase to the 2004/2005 shutdown.
3.
AOB
- Next meeting: Date to be agreed—preferred options were 11am, Wednesday 11th December or 3pm, Thursday 12th December.